Strathy North

  • Category: Renewables
  • Energy type: Onshore wind
  • Project type: Project

Strathy North wind farm site is located approximately 7km from Strathy village, Sutherland, in an area of commercial forestry plantation.

  • 33 turbine project
  • received consent from Scottish Ministers in November 2011
  • now under construction
Your browser is out of date and is no longer capable of displaying video. Please upgrade when possible.

Strathy North wind farm - winter 2014 project update

Strathy North wind farm site is located approximately 7km from Strathy village, Sutherland, in an area of commercial forestry plantation. In this short video, project manager Rod Crawford and liaison manager Ruth Liddicoat provide an update on how work is progressing.

Watch the video

Community

We recognise that our investments in new electricity generation benefit from the cooperation of the local community in a variety of ways, particularly during the construction phase. In recognition of this, our policy is to establish long-term funds to support community projects in areas where we are developing generation projects.

There are two local funds associated with Strathy North wind farm:

Strathy and Armadale Fund
This one-off lump sum fund of £228,000 was launched in April 2014 and is ring-fenced for the Strathy and Armadale Community Council area which 'hosts' the project. The fourth round of grant applications closes on 30 April 2015 with decisions being made on 24 June 2015. For more information click here.

Community Fund Advisory Panel Strathy ArmadalePictured: Strathy and Armadale Fund Panel

Joint Fund
This annual fund of £170,000 (for the 25 year operational life of the wind farm) was launched in October 2014. It is shared by the Community Council areas of Strathy and Armadale; Bettyhill, Strathnaver and Altnaharra and Melvich. The first round of grants were awarded in January 2015, with the second round of applications closing on 28 February for decisions to be made on 15 April 2015. For more information click here.

An additional £170,000 will be provided annually into SSE's Highland Sustainable Development Fund from the Strathy North project to support strategic projects which benefit Highland communities, with priority given to locations near our renewable developments.  For more information click here.

Latest news

The turbine deliveries for Strathy North wind farm started during week commencing 9 February 2015.

Deliveries are arriving by ship into Scrabster harbour and are then transported along the A836 north coast road to our site entrance at Baligill, just east of Strathy village.

The journey between Scrabster and Baligill is taking around an hour, although this can vary with weather and traffic conditions, and all turbine deliveries are escorted with access maintained for emergency vehicles at all times.

For more information on the turbine deliveries please click on the information poster below.


Strathy North Turbine Delivery V2

Project overview

Strathy North is a 33 turbine wind farm located in a commercial forestry plantation called Strathy Forest, approximately 7km south of Strathy Village, in north Sutherland. It was consented by the Scottish Government in November 2011 and is now under construction.

In July 2013 we started 'enabling works' in order to prepare the site for the main construction phase of the project. These works involved (amongst other things) building a new access track to the site entrance to bypass Strathy village.

In February 2014 we appointed RJ McLeod as our civil contractor for the main construction works. They built the tracks on site and spur roads out to each of the turbine locations as well as the turbine bases. The civil works are now virtually complete and RJ McLeod is handing over its role as principal contractor to Senvion, our turbine supplier, who will manage the delivery and erection of the turbines.

The turbine deliveries started in February 2015 and should be finished by the end of the summer, with the site being fully operational towards the end of 2015.

More information

Project information

Background
In January 2007 we submitted a proposal to the Scottish Government for a 35 turbine wind farm at Strathy Forest, approximately 7km from Strathy Village in Sutherland. Since lodging this application we removed two turbines from the design, in response to feedback, and submitted an Addendum in November 2010 to the Scottish Government for a smaller 33 turbine scheme.

We worked closely with the Scottish Government and key consultees throughout the planning process to review responses received and where possible, address the points raised. On 10 May 2011 The Highland Council (a key consultee to the Scottish Government) held a special planning committee meeting to discuss the Strathy North wind farm proposal and provide their response to the Scottish Government. The Council supported the planning report which recommended 'no objection' to the proposal, and on 22 November 2011 consent for the Strathy North proposal was granted by the Scottish Government.

Forestry works
The Strathy North site is located in an area of commercial forestry plantation. In October 2012 we began the first phase of forestry works using a technique called 'keyholing' which targets and removes specific areas of plantation, such as those on the access track routes and turbine base areas, to help open up access to different areas of the site for construction. A mixture of mulching (to produce wood-chipped areas on site) and conventional timber harvesting was used to do this, in line with the site's Habitat Management Plan.

A few loads of harvested timber have been directed to Forsinain, to assist the local sawmill, with the remainder stockpiled whilst it is gradually extracted.

The forestry works will continue into the operational phase of the wind farm, involving a mix of mulching and felling, to gradually clear the commercial forestry on site. The eastern part of the site will also be replanted with native woodland, in addition to other habitat work such as peatland restoration to the south of the site.

Enabling works
In July 2013 we started ‘enabling works’ to prepare the site for the main construction phase of the project. These works were undertaken by highland civil contractor, RJ McLeod, and involved the following:

  • Installing a temporary bridge (at Dallangwell) near the site entrance 
  • Building a platform for the on-site substation 
  • Opening a borrow pit to acquire rock and stone 
  • Minor on-site road works (between borrow pit and substation area) 
  • Building the new access track from Baligill (to bypass Strathy village)

The new access track that was built from Baligill on the A836 north coast road, to join up with the Bowside track which leads to site, was an important element of the preparatory works. This new track ensures that construction traffic and turbine deliveries associated with the main works can bypass Strathy village.

Main construction works
In February 2014, SSE appointed Highland civil engineering firm RJ McLeod as its principal contractor for the main construction works at Strathy North wind farm. Work started on the main access track through the site, and then the spur roads out to each of the turbine locations and hard-standing areas were built. In May 2014 the 33 turbine bases began to be developed and this involved excavating the foundations and building a steel lattice framework for each base which was then poured with concrete. The final bases will be completed in February/March 2015.

The on-site substation which will initially receive the power from the site and release it onto the grid is gradually being developed, and the majority of cabling works to lay the connections out to each of the turbine bases were completed by February 2015..

Turbine deliveries will start during week commencing 9 February 2015 and should be finished by the end of the summer, with the site being fully operational towards the end of 2015.

Involving local businesses

Our approach
We are committed to maximising the benefits and opportunities for local businesses and communities from the Strathy North project.

Business opportunities event
In February 2014 we held a Business Opportunities event in Strathy Village Hall to help local firms find out more about the upcoming opportunities associated with the £109m project. Over 50 businesses attended from across the north Highlands to talk to SSE's project construction team and principal civil contractor, RJ McLeod, about the services they could offer and how to get involved with the project. Our Open4Business procurement team was also on hand to help businesses register on SSE's highland portal at www.sseopen4business-highlands.com where Strathy North project opportunities will be advertised.

Strathy North - Business Opportunities Event
Feedback from the event was very positive, and Janette MacKay, Strathy & Armadale Community Council Chairperson, said: “SSE has worked hard to ensure that the event was well organised and relevant to the local area, and the feedback from within the community has been excellent. There are a growing number of people from the immediate communities of Strathy, Bettyhill and Melvich who have received work and long-term employment from the project either during the ‘enabling’ period or since the main construction phase has started, in addition to the bigger businesses in the wider north coast area. In fact, there are more people than we realised who are getting jobs from the project."

To see a video from the event, please click the link here.

Using local services
We have already been using a wide variety of local services in the area during the enabling works phase of the project. These include the hotels and B&Bs, restaurants and cafes, shops, garages and petrol stations, and local village halls for meetings and events. This is expected to continue into the main construction phase of works.

Involving local businesses
One of the key benefits from a project like Strathy North is the opportunities it provides to local businesses to get involved. Already, since the enabling works started in July 2013, the project has already generated in excess of £7m of investment to the Sutherland and wider Highland economy. Rural businesses at all levels have benefitted, from small operators like the Melvich shop, Clean Bees cleaning company in Bettyhill, accommodation providers in the local area and local trades people such as joiners and fencers, through to larger businesses within the wider area including:

  • Charles Angus Engineers (Thurso) 
  • John Gunn and Sons Ltd (Kirkton Quarry - Melvich)
  • E&M Engineering (Scrabster) 
  • GMR Henderson (Wick) 
  • MM Miller (Wick)
  • Simpson Oils (Thurso)
  • Waverley Plant Hire (Golspie)

This is in addition to Highlands civil engineering firm, RJ McLeod, which was awarded a £14m contract in February 2014. For more information click here.

In May 2014 SSE contractor RJ McLeod engaged the services of John Gunn & Sons – operator of the Kirkton Quarry in Melvich – in a landmark seven-figure deal for the local firm. The quarry will provide concrete for the turbine bases at SSE’s Strathy North wind farm, which is currently under construction nearby, and also enable its owners to invest in a new batching plant. This will allow the materials required for the construction project to be mixed at the quarry before being delivered to the wind farm site. For more information click here.

The project has also created a number of permanent new jobs in the local area, and indirectly supported many others.

M9R3136